Valid 220-1102 Dumps shared by ExamDiscuss.com for Helping Passing 220-1102 Exam! ExamDiscuss.com now offer the newest 220-1102 exam dumps, the ExamDiscuss.com 220-1102 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com 220-1102 dumps with Test Engine here:
A change management review board denied an administrator's request for change. The administrator had provided the purpose and scope of the change, the date and time, and impacted systems with the risk analysis. Which of the following should be included to approve this change?
Correct Answer: C
A rollback plan is essential for a change to be approved by a change management review board. It outlines the steps to reverse a change in case something goes wrong, minimizing downtime and mitigating risk. Other items like end-user acceptance and cost analysis are important but not typically the deciding factor for approval. Reference: CompTIA A+ 220-1102 Exam Objectives, Domain 4.2 Operational Procedures - Change Management