What is the correct sequence of steps involved in scheduling a threat intelligence program? 1. Review the project charter 2. Identify all deliverables 3. Identify the sequence of activities 4. Identify task dependencies 5. Develop the final schedule 6. Estimate duration of each activity 7. Identify and estimate resources for all activities 8. Define all activities 9. Build a work breakdown structure (WBS)
Correct Answer: A
The correct sequence for scheduling a threat intelligence program involves starting with the foundational steps of defining the project scope and objectives, followed by detailed planning and scheduling of tasks. The sequence starts with reviewing the project charter (1) to understand the project's scope, objectives, and constraints. Next, building a Work Breakdown Structure (WBS) (9) helps in organizing the team's work into manageable sections. Identifying all deliverables (2) clarifies the project's outcomes. Defining all activities (8) involves listing the tasks required to produce the deliverables. Identifying the sequence of activities (3) and estimating resources (7) and task dependencies (4) sets the groundwork for scheduling. Estimating the duration of each activity (6) is critical before developing the final schedule (5), which combines all these elements into a comprehensive plan. This approach ensures a structured and methodical progression from project initiation to execution.References: * "A Guide to the Project Management Body of Knowledge (PMBOK Guide)," Project Management Institute * "Cyber Intelligence-Driven Risk," by Intel471