Valid 1D0-61A Dumps shared by ExamDiscuss.com for Helping Passing 1D0-61A Exam! ExamDiscuss.com now offer the newest 1D0-61A exam dumps, the ExamDiscuss.com 1D0-61A exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com 1D0-61A dumps with Test Engine here:
Your customer scheduled a meeting to discuss a project you are managing. Early testing indicates that there are currently quality problems with some of the more complex features. The customer stated that quality and budget are his two main concerns: The project must be developed within budget and must be very high quality. When you asked the customer if he would be willing to extend the deadline to meet his objectives, he stated this was not possible. What adjustment to the project triangle components can you suggest to meet your customer's needs?