Which of the following is a quantative method for completing a risk assessment and an alternative to using an impact scale?
Correct Answer: D
Explanation P. 133 of the study guide says 'it is also possible for organisation to use a quantative method where they quantify the loss in terms of monitory value instead of an impact figure'. Rating 1-5 is incorrect because this is the same as an impact scale. Impact analysis is wrong because this isn't quantative. 4Ts are the ways you can mitigate risks.