Looking at stage 8 of the procurement and supply cycle, what does TCA mean?
Correct Answer:
When evaluating offers, it is important to remember that the best price may not be the lowest. To ascertain that; the total cost of Acquisition TCA (the cost a buyer bears for placing orders and re-ceiving a product from a supplier) should be uncovered and compare against offers received. Things to consider that might make up the total cost of acquisition are; 1) logistics and handling costs 2) Cost of requisition 3) Rework 4) stock cost 5) Delay 6) Inspection 7) customer services 8) consumables 9) Training & support