Scott is a procurement manager who is evaluating a bid from a supplier to provide a new IT system to his office that will be used by 100 employees. He is considering the total life-cycle costs. Which of the following should Scott consider? Select THREE
Correct Answer: A,C,D
total life-cycle costs include; acquisition costs, maintenance and training. Added value and functional fit are quality criteria that should also be evaluated when selecting a supplier, but do not fall under total life-cycle costs. Note: total life cycle costs and whole life asset management are the same thing. You may see both terms used in the exam. I think CIPS is moving more towards Whole Life Asset Management now as the preferred vocabulary but they're the same thing.