Valid P3 Dumps shared by ExamDiscuss.com for Helping Passing P3 Exam! ExamDiscuss.com now offer the newest P3 exam dumps, the ExamDiscuss.com P3 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com P3 dumps with Test Engine here:
YGH has recently completed a post completion audit on a five year contract that has only recently come to a conclusion. The main finding was that the project delivered most of the expected benefits, but that it cost significantly more to implement than had been anticipated at the project appraisal stage. YGH would not have proceeded if the true cost had been known at that stage. The project was the responsibility of the production department, which is presently managed by G. When the project was proposed, the production department was managed by H. H is now YGH's Director of Operations. How should the finding from this post completion audit be interpreted?