Question 47/150

Select the appropriate task to complete section 2.2 of the work breakdown structure (WBS) below:
2 Technician
2.1 Install cabling
2.2 __________
2.3 Activate wireless

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (150q)
Question 1: For a building with up to 100,000 sq. ft. of usable floor sp...
Question 2: A building has six floors plus a basement. Each floor is 929...
Question 3: What is the MINIMUM distance from the edge of a pool or othe...
Question 4: What type of fiber optic cable is manufactured to protect in...
Question 5: The (FCC) CC Docket 88-57
Question 6: You are designing a firestop system for a hospital with seve...
Question 7: Arial suspension strands and cable should usually be placed ...
Question 8: Which of the following is an address used to uniquely identi...
Question 9: Which of the following Right-of-Way shares characteristics o...
Question 10: The MOST common medium used to provide service to the access...
Question 11: Which of the following is a wire and cable manufacture's org...
Question 12: The concept of the "security quandary" is based on providing...
Question 13: Exhibit: In this future marina layout, assuming that there a...
Question 14: Which of the following is NOT a primary method of transporti...
Question 15: In a hallway with normal traffic, ceiling mounted speakers s...
Question 16: Often associated with raised flooring, a(n) ________ may con...
Question 17: The electromagnetic spectrum of visible light lies in the __...
Question 18: A backbone star topology shall have no more than______ level...
Question 19: An open office design is made up of three furniture clusters...
Question 20: Which one of the following would meet the minimum horizontal...
Question 21: You must extend a video systems backbone coax cable that was...
Question 22: Which of the following is an undesirable electromagnetic eff...
Question 23: The CP can be used as a TP for under the carpet cabling....
Question 24: Which of the following would be the medium duty concentrated...
Question 25: The information technology system (ITS) designer should desi...
Question 26: To reduce the chance of an accidental dig-up, plastic warnin...
Question 27: You have discovered a common mode current on the metallic ca...
Question 28: How much area of wall space is needed in the telecommunicati...
Question 29: A conduit run is installed from the ER to a TR. It has two (...
Question 30: A ________ eliminates the need to remove or install material...
Question 31: For TRs that contain active equipment, what is the minimum t...
Question 32: The standard floor space coverage area for each building aut...
Question 33: Certain systems must exist relative to bonding and grounding...
Question 34: Assume that the optical power transmitted by a 62.5/125 mult...
Question 35: Using the "pathway design" for horizontal cable distribution...
Question 36: Color codes for cross-connections fields have been used for ...
Question 37: Time division multiplexing (TDM) systems are designed to tra...
Question 38: Within building automation hardware systems, there is a hier...
Question 39: In a computer or control room where the plenum is used for h...
Question 40: Which class of the system applies when the premise only has ...
Question 41: "A single outlet utilizing a dedicated phase, neutral, and g...
Question 42: The propagation and path loss of radio signals in the target...
Question 43: Which active DAS component is responsible for coupling input...
Question 44: The RECOMMENDED balanced twisted-pair cable for building bac...
Question 45: Loose-buffered cables are constructed so the fibers are deco...
Question 46: The inadvertent transposition of two conductors of separate ...
Question 47: Select the appropriate task to complete section 2.2 of the w...
Question 48: You are designing a restaurant located within a retail mall....
Question 49: An offset in a conduit run should be considered the equivale...
Question 50: Which device uses circulators or diplexer filters to separat...
Question 51: An isolated ground is used to:
Question 52: A "sag" is a decrease in normal root mean square (rms) volta...
Question 53: In a telecommunication room (TR), the ________ is the facili...
Question 54: In a telecommunications room (TR), the MINIMUM bottom edge h...
Question 55: The maximum vertical rise is the distance over which the cab...
Question 56: Which of the following statements best describes what a back...
Question 57: One interior TTY must be provided at locations defined as pu...
Question 58: Vertical conduit masts (with approved service heads) are lim...
Question 59: In order to maximize its ability to send and receive, an ant...
Question 60: What is the International Organization for Standardization/I...
Question 61: A properly designed distributed paging system will provide a...
Question 62: An isolated ground receptacle may be identified by:...
Question 63: What is the MAXIMUM horizontal cable length permitted for ce...
Question 64: A fire ________ is a contained area that is completely enclo...
Question 65: What type of material does NOT support combustion even under...
Question 66: The MINIMUM separation distance between grounded metal telec...
Question 67: What is the expected life cycle, in years, of building autom...
Question 68: A common mode (CM) signal can be converted to a differential...
Question 69: Optical transmitters are typically one of the following type...
Question 70: You are working with the Sheriff's Department to develop a p...
Question 71: From a 1000 ft (305 m) roll of optical fiber, how many MAXIM...
Question 72: During a site survey you notice that several CRT displays in...
Question 73: Which of the following does NOT describe one of the four mai...
Question 74: You are designing a DAS that will support five buildings on ...
Question 75: You are extending 1000 MHz video service from your existing ...
Question 76: A furniture cluster with 26 requires a MINIMUM of how many m...
Question 77: Exhibit: (Exhibit) A pay telephone using coins needs to be i...
Question 78: Lose buffered fiber optic cable generally have a 900 micron ...
Question 79: Horizontal slack in the form of bundled loops have been know...
Question 80: Which of the following is NOT provided by the ac grounding e...
Question 81: When selecting poles for aerial telecommunications facilitie...
Question 82: You have been asked what the estimated power cost will be pe...
Question 83: A ______ intercepts a file and stores it temporarily in queu...
Question 84: Using the sound pressure level (SPL) method of approximating...
Question 85: In what year was BICSI formally incorporated?...
Question 86: Within a data center, how many concentric layers are conside...
Question 87: What are the three typical voltages used in centrally amplif...
Question 88: Geographically speaking, a __________ covers an area associa...
Question 89: You must place CAT6 cable above a factory floor with automat...
Question 90: The three electronic security system (ESS) concepts the cons...
Question 91: When placing an optical fiber cable in the horizontal optica...
Question 92: At the end of the third week of a project, the actual cost o...
Question 93: You are designing a DAS system that has a requirement to sup...
Question 94: Exhibit: A pay telephone using coins needs to be installed i...
Question 95: The minimum door size should be which of the following?...
Question 96: Power outlets should be place every 10 feet around the perim...
Question 97: A telephone facility and an electrical facility are required...
Question 98: Which of the following are general power requirements for al...
Question 99: Which layer of the OSI model covers physical cable connectio...
Question 100: As a general guideline in premises applications for backbone...
Question 101: When developing a safety plan, consider all of the following...
Question 102: You are preparing to test newly installed open office cablin...
Question 103: You must place a cable between 2 equipment locations with se...
Question 104: You have just finished a design calling for 15 telecommunica...
Question 105: You are designing a large equipment room (ER) that will hous...
Question 106: The headend has several audio-video playback devices within ...
Question 107: A campus backbone design linking two buildings requires that...
Question 108: Which type of protection for electrical power stations provi...
Question 109: What is the testing frequency of a Category 6/Class E cable?...
Question 110: The recommended MAXIMUM value for the bonding resistance bet...
Question 111: An Interconnection is a connection scheme between cabling ru...
Question 112: Premises optical fiber links should be tested:...
Question 113: Which of the following is NOT a primary type of DAS antenna?...
Question 114: When specifying telecommunications outlet boxes, all of the ...
Question 115: You are placing an entrance cable between two buildings conn...
Question 116: Phase difference is the relationship in time between two wav...
Question 117: OSP cables routed inside a building are influenced by fire c...
Question 118: A reasonable approximation for the signal speed in 100 ohm b...
Question 119: The American Public Works Association has adopted the color ...
Question 120: What type of address is 00-A1-C3-52-CE-11?...
Question 121: In a run requiring 15 m (50 ft) of cable between the floor d...
Question 122: You are designing a nurse call system for a health care faci...
Question 123: Cementitious materials are ________ based materials....
Question 124: What is the PERT estimate (in hours) for project design wher...
Question 125: Optical fiber all-dielectric cables have an additional advan...
Question 126: Within a commercial office building of 2300 sq m (25000 sq f...
Question 127: Which of the following is true about screened twisted pair c...
Question 128: A vertical conduit mast should not extend above a roof line ...
Question 129: Exhibit: This diagram illustrates an example of a: (Exhibit)...
Question 130: Cables are installed in a ceiling in a straight line. The ce...
Question 131: You are designing a four story retail mall and multiple soun...
Question 132: Data representation including code translations, compression...
Question 133: If the usable floor space is unknown, then deduct ________ p...
Question 134: You are designing a nurse call system for an assisted care f...
Question 135: You are reviewing a building backbone design with a vertical...
Question 136: Premises centralized multimode optical fiber can be installe...
Question 137: The recommended MINIMUM number of conduits connecting two lo...
Question 138: If you have a 30 cm (12 in) wide data tray, what does ANSI/T...
Question 139: For design purposes, which of the following would be the typ...
Question 140: As a wireless designer, you have been tasked with designing ...
Question 141: The RJ-45 is now known as the 8P8C style connector, per the ...
Question 142: Which is NOT a type of contract?...
Question 143: The purpose of QoS on an IP network is for:...
Question 144: What is the minimum clear working space between equipment an...
Question 145: What is the minimum parallel separation distance from a UTC ...
Question 146: What is the typical slab thickness requirement for a two lev...
Question 147: When considering the DAS, which component acts as a bidirect...
Question 148: All entrance conduits should be equipped with a plastic or n...
Question 149: What is the horizontal separation, in well tamped earth, req...
Question 150: In the customer's environment, an ITS designer should avoid ...