You are in a backlog refinement meeting with the development team and the product owner. You review a story for an integration involving a third-party system. A payload will be sent from the Appian system through the integration to the third-party system. The story is 21 points on a Fibonacci scale and requires development from your Appian team as well as technical resources from the third-party system. This item is crucial to your project's success. What are the two recommended steps to ensure this story can be developed effectively?
Correct Answer: C,D
Comprehensive and Detailed In-Depth Explanation:This question involves a complex integration story rated at 21 points on the Fibonacci scale, indicating significant complexity and effort. Appian Lead Developer best practices emphasize effective collaboration, risk mitigation, and manageable development scopes for such scenarios. The two most critical steps are:
* Option C (Maintain a communication schedule with the third-party resources):Integrations with third-party systems require close coordination, as Appian developers depend on external teams for endpoint specifications, payload formats, authentication details, and testing support. Establishing a regular communication schedule ensures alignment on requirements, timelines, and issue resolution.
Appian's Integration Best Practices documentation highlights the importance of proactive communication with external stakeholders to prevent delays and misunderstandings, especially for critical project components.
* Option D (Break down the item into smaller stories):A 21-point story is considered large by Agile standards (Fibonacci scale typically flags anything above 13 as complex). Appian's Agile Development Guide recommends decomposing large stories into smaller, independently deliverable pieces to reduce risk, improve testability, and enable iterative progress. For example, the integration could be split into tasks like designing the payload structure, building the integration object, and testing the connection- each manageable within a sprint. This approach aligns with the principle of delivering value incrementally while maintaining quality.
* Option A (Acquire testing steps from QA resources):While QA involvement is valuable, this step is more relevant during the testing phase rather than backlog refinement or development preparation. It's not a primary step for ensuring effective development of the story.
* Option B (Identify SMEs for UAT):User acceptance testing occurs after development, during the validation phase. Identifying SMEs is important but not a key step in ensuring the story is developed effectively during the refinement and coding stages.
By choosingCandD, you address both the external dependency (third-party coordination) and internal complexity (story size), ensuring a smoother development process for this critical integration.
References:Appian Lead Developer Training - Integration Best Practices, Appian Agile Development Guide
- Story Refinement and Decomposition.