An admin-level user has created a group status for tasks in projects. The admin notices in testing that the custom task status is only available in some of the projects with assigned Marketing team members.
Why is the group status missing in some projects?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (29q)
Question 1: An Adobe Workfront system administrator is asked to fix an e...
Question 2: What does the Cost Performance Index (CPI)of a project in Wo...
Question 3: A customer has a set of users who need to review and approve...
Question 4: A system administrator is using layout templates to optimize...
Question 5: A Chart report was created, but the client wants to display ...
Question 6: A marketing team has created a new project template for a Pr...
Question 7: An admin-level user has created a group status for tasks in ...
Question 8: A project manager wants to use Portfolios and Programs to or...
Question 9: A client requires that employees account for any "breaks" du...
Question 10: An admin-level user recommends assigning the role Reviewer &...
Question 11: A system administrator is using Dashboards to streamline how...
Question 12: Which reporting element has an option of conditional formatt...
Question 13: Which component may be added to Canvas Dashboards, but not l...
Question 14: In which scenario would an administrator use a request queue...
Question 15: How can a project manager ensure that progress on the board ...
Question 16: An Adobe Workfront System Administrator has been asked to co...
Question 17: Aside from predecessors, resource manager assignments, and s...
Question 18: A system administrator has been asked to onboard several ext...
Question 19: What is one of the primary benefits to setting up an automat...
Question 20: What is the hierarchical relationship between a Queue Topic ...
Question 21: A task includes an approval requiring a lead designers appro...
Question 22: A client has employees based in both India (1-10 1ST) and th...
Question 23: A Workfront developer is tasked with building a new custom f...
Question 24: A client wants to keep track of project metrics based on the...
Question 25: A customer wants to connect Adobe Workfront with their Jira ...
Question 26: Several team managers within an organization have complained...
Question 27: A marketing agency uses Workfront to plan and execute projec...
Question 28: One of the most requested connections for Adobe Workfront is...
Question 29: On which types of objects can time be recorded in Workfront?...