Referring to the Supply and Demands shown in the graphic, and taking priorities into consideration, which scheduled receipts (SR) will be allotted to Demand 2?
Correct Answer: C
Considering that Demand 2 has a higher priority than Demand 1 (as indicated by "High" versus "Medium"), it will be allocated available supplies before Demand 1, following the priority rules. SR1 is scheduled for Monday and will likely be allocated to Demand 1, being the first demand of the week. For Demand 2, SR2 is the nextavailable and will fulfill 200 units. Since Demand 2 requires 300 units and SR2 only supplies 200, the next available SR, which is SR3, will cover the remaining 100 units needed. ReferencesAllocation of supplies to demands in Kinaxis RapidResponse takes into account both the chronological order of the scheduled receipts and the priority of the demands. This is consistent with Kinaxis's allocation rules as outlined in the RapidResponse documentation. References: * The Kinaxis RapidResponse documentation indicates that scheduled receipts are allotted based on priority and availability, with earlier dates being allocated first to meet high-priority demands12.