Valid ISTQB-CTFL Dumps shared by ExamDiscuss.com for Helping Passing ISTQB-CTFL Exam! ExamDiscuss.com now offer the newest ISTQB-CTFL exam dumps, the ExamDiscuss.com ISTQB-CTFL exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com ISTQB-CTFL dumps with Test Engine here:
Consider the followingiteration planning taskswhere a tester can provide value: * Break down user stories into tasks (particularly testing tasks) * Estimate test effort for all testing tasks * Identify and refine functional and non-functional aspects of the test object Which ONE of the following tasks should be ADDED to the above list?
Correct Answer: B
Comprehensive and Detailed In-Depth Explanation:During iteration planning, testers provide input on risk analysis, testability, and the feasibility of test automation.Participating in risk analysis (B)helps identify areas needing more extensive testing. * (A) is incorrectbecause the test strategy is usually set at a higher level (project or release level). * (C) is incorrectas release planning is broader than iteration planning. * (D) is incorrectsince writing user stories is mainly the responsibility of theproduct owner, though testers contribute to defining acceptance criteria. Risk-based test prioritizationensures testing efforts are aligned with business needs and software risks.